• WOODLAND PARK MODERNIZATION

     
     
    Project Overview
     
    The Woodland Park Middle School Modernization project developed around a program need to enlarge the highly-elected art facilities and student support services.  In this project, an addition to the art classroom also includes a full modernization to include new student creation stations, a teacher's demonstration area, and large item storage and display capacity.  The student services addition and modernization portions of the project include an additional conference room, new staff restrooms, and a beautification of the front entry which also addresses water-intrusion issues on the Administration building.  Accessibility and safety/security issues are also addressed as required by the Division of the State Architect. 
     
    Project Commencement:  Phase 1 - July 2013; Phase 2 - October 2013
     
    Project Completion:  Phase 1 - August 2013; Phase 2 - February 2014
     
    Budget From Proposition K Funds:  $1,210,066
     
    Expenditures to Date:  $1,210,066