Project Overview: Shade Shelter Project:
There are ever-increasing needs for shade at existing school campuses for the safety of the students at lunch and with physical education programs. The following campuses were selected for installation of new shade shelters: Woodland Park Middle School, San Marcos Middle School, San Elijo Elementary and Twin Oaks Elementary.
Project Commencement: June 2015
Project Completion: August 2015
Budget from Proposition K funds: $982,004
Expenditures to date: $982,004
Expenditures by Site
Woodland Park Middle School: $302,631
San Marcos Middle School: $197,975
San Elijo Elementary: $230,937
Twin Oaks Elementary: $250,461