Measure JJ Current Projects

  • Aerial view of a building complex with solar panels and surrounding residential area.

    Aerial 9-28-25

    Construction site with blue barriers and heavy machinery.

    Buildings C/D Construction September ‘25

    Construction site with heavy machinery excavating earth.

    Underground Utilities Site Work September ‘25

    Knob Hill Elementary School Renovation Project

    Project Scope:

    • Renovation of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings

     

    Budget: $94M 

    Construction began Summer 2025

  •  

    A new sports field is under construction on a cloudy day.

    Practice Fields September ‘25

    Construction site with a grid of rebar over yellow sheeting, ready for concrete.

    Tennis Courts September ‘25

    Construction site with workers, machinery, and a building in the background.

    Volleyball Courts September ‘25

    Mission Hills High School Sitewide Athletic Improvements Project

     

    Project Scope:

    • Stadium: Replacement of artificial turf and replacement of synthetic track 
    • Practice Field: Replacement of grass field with artificial turf and installation of field lights
    • Tennis Courts: Replacement of ten (10) tennis courts with eight (8) new post-tension concrete tennis courts and conversion of two (2) existing tennis courts into three (3) beach volleyball courts. New drainage of the surrounding slopes.

     

    Budget: $13.5M - Measure JJ and CFD

    Construction began June 2025

  • An exterior view of a modern school building with the words 'Administration' above the entrance.

    Rendering Front of School

    Aerial view of a large building complex with multiple structures and parking areas.

    Aerial 10-2-25

    An empty basketball court with a trailer parked on it, under a blue sky.

    Phase I – Building H area

    Woodland Park Middle School Renovation Project 

     

    Project Scope:

    • Renovation of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings

     

    Budget: $105.2M - Measure JJ and multiple funding sources

    Construction Began September 26, 2025 for Phase I to include removal of portables 505/506, add temp power, and begin constrcution on Building H.