Alvin Dunn School K8 Conversion
Previous Album
Next Album
Project Overview
Current Project Scope
- Conversion from Elementary to K-8 International Baccalaureate
- Phase 1 (Building B): 14 classrooms
- Phase 2 (Building A): Administration building/35 classrooms
- Phase 3 (Building C): Multipurpose room/gym, kitchen, locker facilities, band facilities
- Removal of all buildings/portables
- Parking lot
- Bus drop-off
- Total square feet: 102,000
- Funding Source: Prop K
- Budget: $17M
- Expenditures: $16.7M (as of 2-28-19)
- Rename school to La Mirada Academy (2018-19)
PROJECT STATUS:
- Phase 1 100% complete
- Phase 2 100% complete
- Phase 3 100% complete