Current
Measure JJ Current Projects
-
Knob Hill Elementary School Reconstruction
Project Scope:
- Reconstruction of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings.
Contractor: Balfour Beatty Construction Co.
Architect: DLR Group
Budget: $94M Measure JJ and multiple funding sources
Construction: Began Summer 2025
May 2026:
Building D: Library/Classrooms

Building C: Classrooms/Support

-
Woodland Park Middle School Renovation
Project Scope:
- Renovation of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings.
Contractor: Lusardi Construction Co.
Architect: HMC Architects
Budget: $105.2M - Measure JJ and multiple funding sources
Construction: Began September 26, 2025
- Phase Interim Housing “Onsite”: May ‘26 – Aug ‘26
- Interim Housing “On Site”
- 6th grade “Satellite Campus” at SMMS for the 2026/27 school year
May 2026: Building H/Science and Classrooms




-
San Marcos High School Sitewide Athletic Improvements Project
Project Scope:
- Stadium: Replacement of artificial turf, including the “D” area. Replacement of synthetic track, shot put area, pole vault, and long jump runways.
- Multi-Purpose Fields: Replacement of grass fields with artificial turf and installation of field lights.
- Beach Volleyball Courts: Addition of three (3) beach volleyball courts.
Budget: $12M - Measure JJ and CFD Funds
Contractor: C.W. Driver LLC
Architect: tBP/Architecture
Construction: May – October 2026
Stadium, Track, and Beach Volleyball

Multi-Purpose Fields