Measure JJ Current Projects

  • Knob Hill Elementary School Reconstruction

     

    Project Scope:

    • Reconstruction of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings.

     

    Contractor: Balfour Beatty Construction Co.

    Architect: DLR Group

    Budget: $94M Measure JJ and multiple funding sources

    Construction: Began Summer 2025

     

    June 2026:

    Bldging C and Food Service

    Food Service Building

    Buildings and Support

    Classrooms, Support, and Library Buildings

    TK/Kinder Drive way

    TK/Kinder Driveway

    New TK Building

    TK Building

  • Woodland Park Middle School Renovation 

    Project Scope:

    • Renovation of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings.

     

    Contractor: Lusardi Construction Co.

    Architect: HMC Architects

    Budget: $105.2M - Measure JJ and multiple funding sources

    Construction: Began September 26, 2025

    • Phase Interim Housing “Onsite”: May ‘26 – Aug ‘26
      • Interim Housing “On Site”
      • 6th grade “Satellite Campus” at SMMS for the 2026/27 school year

    June 2026: Building H/Science and Classrooms

    A multi-story building under construction with scaffolding and heavy machinery on site.

    Construction site with a deep trench dug in concrete, alongside stadium seating.

    Aerial WPMS Building H

     

     

     

     

  • San Marcos High School Sitewide Athletic Improvements Project 

    Project Scope:

    • Stadium: Replacement of artificial turf, including the “D” area. Replacement of synthetic track, shot put area, pole vault, and long jump runways.
    • Multi-Purpose Fields: Replacement of grass fields with artificial turf and installation of field lights.
    • Beach Volleyball Courts: Addition of three (3) beach volleyball courts.

     

    Budget: $12M - Measure JJ and CFD Funds

    Contractor: C.W. Driver LLC

    Architect: tBP/Architecture

    Construction: May – October 2026

    Stadium, Track, Beach Volleyball, and Tennis Courts Resurface

    June 2026:

    Stadium and TrackA construction crew works on a sports field, laying down new turf.

    An empty outdoor court with a chain-link fence and a building in the background.

    Multi purpose field