Current
Measure JJ Current Projects
-
Knob Hill Elementary School Renovation
Project Scope:
- Renovation of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings.
Contractor: Balfour Beatty Construction Co.
Budget: $94M Measure JJ and multiple funding sources
Construction: Began Summer 2025

Bldg C – Feb ‘26

Bldg D – Feb ‘26

Bldg E – Feb‘26
-
Woodland Park Middle School Renovation
Project Scope:
- Renovation of existing buildings, site reconfiguration, and replacement of portable buildings with permanent buildings.
Contractor: Lusardi Construction Co.
Budget: $105.2M - Measure JJ and multiple funding sources
Construction: Began September 26, 2025 for Phase I to include removal of portables 505/506, add temp power, and begin construction on Building H.
Bldg H Retaining Wall – Feb ‘26
Bldg H – Feb ‘26
Bldg D5 - Feb ‘26

-
San Marcos High School Sitewide Athletic Improvements Project
Project Scope:
- Stadium: Replacement of artificial turf, including the “D” area. Replacement of synthetic track, shot put area, pole vault, and long jump runways.
- Practice Fields: Replacement of grass fields with artificial turf and installation of field lights.
- Beach Volleyball Courts: Addition of three (3) beach volleyball courts.
Budget: $12M - Measure JJ and CFD Funds
Contractor: C.W. Driver LLC
Construction is scheduled to begin June 2026